Project Overview

TAR on field with high requirement for pipework replacement including all associated pipe supports.

Scope

  • Dimensional Survey, design and fabrication of 72 pipe spools plus supports for installation during TAR
  • Management of material supply, fabrication, inspection release and PED for all pipework
  • Scope included TAR critical path scope – replacement of Closed Drain Header
  • Scopus devised strategy to minimise TAR scope including parallel installation of sections of header

Benefits delivered by Scopus:

  • 10 spools installed pre-TAR and 37 spools installed during TAR saudemasculina.pt
  • Installation of replacement Closed Drains Header – approx. 100m of 8” pipework
  • First-time-fit of spools
  • Increased uptime, no rework costs
  • TAR schedule maintained