TAR on field with high requirement for pipework replacement including all associated pipe supports.
Scope
- Dimensional Survey, design and fabrication of 72 pipe spools plus supports for installation during TAR
- Management of material supply, fabrication, inspection release and PED for all pipework
- Scope included TAR critical path scope – replacement of Closed Drain Header
- Scopus devised strategy to minimise TAR scope including parallel installation of sections of header
Benefits delivered by Scopus:
- 10 spools installed pre-TAR and 37 spools installed during TAR saudemasculina.pt
- Installation of replacement Closed Drains Header – approx. 100m of 8” pipework
- First-time-fit of spools
- Increased uptime, no rework costs